Set 95 — Linear Programming — Setting Up Constraints

10 questions · 🧪 Test Mode · ⏱ 15 min

🧪 Test Mode
0 answered · 10 remaining
15:00

🧪 Test Mode — answers hidden until you finish

Linear Programming — Setting Up Constraints
1 / 10

WAEC 2019

A factory makes two products X and Y. Each X needs 2 hours labour and each Y needs 3 hours. Total labour available is 120 hours. Each X needs 4 kg material, Y needs 2 kg. Total material = 100 kg. At least 10 of each must be made. Write the constraints.